Introduction to the method of installation and disassembly of small tablet press

How to install and disassemble small tablet presses:

Introduction: The small tablet press presses various granular raw materials into pellets, which is suitable for laboratory trial production or small batch production of various tablets, sugar tablets, calcium tablets and the like. It is a small bench-top electric (manual) continuous tableting machine. The machine is equipped with a die, the filling depth of the material and the thickness of the tablet can be adjusted.

First, use and characteristics:

TDP-1.5 single punching machine can compress powdery granular materials into tablets, which can be widely used in pharmaceutical factories, chemical plants, hospitals, scientific research units, laboratory trial production and small batch production.

The machine has excellent performance, strong adaptability, convenient use, easy maintenance, small size, light weight, and can also be shaken when there is no electricity. This machine only installs a die, the filling depth of the material, the thickness of the tablet can be adjusted, can adapt to the requirements of the pharmaceutical industry to suppress various Chinese and Western medicine preparations and other industries to suppress the requirements of various similar products, and is widely accepted by users in various industries. Welcome.

Second, the tablet press installation and wiring:

1. The tablet press is mounted on a solid wooden workbench (also mounted on a concrete platform) with three M12 anchor screws. The height of the work surface to the ground is about 600 mm (hand-operated, easy to operate). In order to facilitate the disassembly and repair, the position piece corresponding to the lower punching rod on the wooden workbench should also have a hole of about 35 mm in diameter.

2. Connect the motor to the ground wire before turning on the motor power to ensure safety. Remove the V-belt, turn on the motor power, and start the motor to see if the motor rotates in the correct direction (the direction of rotation of the motor shaft should be opposite to the direction of the arrow on the shield or handwheel). If the direction of rotation is wrong, connect the cable separately and then the V-belt. Installed.

Third, the loading and unloading of the die and the adjustment during tableting:

1. Installation of the die (1) Install the upper punch: loosen the lower punch and fix the screw, turn the handwheel to raise the lower punching rod to the high position of the zui, and insert the lower punch into the hole of the lower punching rod (note the notch of the lower punch) Align the bevel with the lower fastening screw and insert it into the bottom. Then tighten the lower fixing screw.

(2) Install the lower punch: Loosen the upper punching tightening nut, insert the upper punching rod into the hole of the upper punching rod, insert it to the end, use a wrench to clamp the hexagonal part of the upper part of the punching rod, and tighten the upper punching tightening nut.

(3) Install the middle mold: Loosen the middle mold fixing screw, put the middle mold into the hole of the middle mold plate, and make the lower punch into the hole of the middle mold, press the bottom and then tighten the middle mold fixing screw. When placing the mold, pay attention to flatten the middle mold to avoid jamming when the skew is placed and damage the hole wall.

(4) Turn the handwheel by hand to slowly lower the upper punch into the middle die hole to observe whether there is collision or friction. If there is collision or friction, loosen the middle die plate fixing screws (two) and adjust the middle die table. The position of the plate is fixed so that the upper punch enters the middle die hole, and then the middle die plate fixing screw is tightened, so that the upper punch enters the middle die without collision or friction for the installation.

2. Adjust the output of the film and turn the handwheel to raise the lower punch to the high position of the zui. Observe whether the lower punch surface is aligned with the plane of the middle die (or both high and low will affect the film). If not, loosen the butterfly screw. Loosen the gear platen and transfer the upper adjustment gear so that the lower punch surface is aligned with the plane of the middle mold. Then press the pressure plate up and tighten the butterfly screw.

At this point, the handwheel is shaken by hand, and the empty car runs for more than ten revolutions. If the machine is running normally, the pressure can be fed and the next step can be adjusted.